airport update from Ed Wright - 7/11/07

New posts

Kurt

Admin
Full article - http://westbayflorida.blogspot.com/2007/07/404-permit.html


The Airport Authority has been waiting for a final permit from the U.S. Army Corps of Engineers (USACE) in order to move forward with construction of the new airport.

Everyone who has been following this project closely asks one question: When is the 404 permit coming?

Last week the News Herald reported that there were three issues that needed to be resolved before the permit was released.
 