Public Works Updates

New posts

steel1man

Beach Fanatic
Walton County
CR285
The contractor has completed the placement of limerock in the widening areas. Density testing is scheduled for the week of October 17, 2016. Users of CR285 should expect temporary lane closures and delays.

Western Lake Pedestrian Bridge
The contractor has established a lay down area for equipment and materials on the project’s western end. Erosion controls are being installed both in and around Western Lake. Clearing for the multi-use path has begun on the east end of the project. The fabrication of the bridge components is scheduled to begin the week of October 17, 2016. Users of CR30A in the construction zone may experience temporary delays.
 
New posts


Sign Up for SoWal Newsletter












                               
Back
Top